Dalrymple Road Pavement Rehabilitation and Reconstruction

Dalrymple Rd

 

 

 

 

 

 

 

 

Client: Townsville City Council
Project: Dalrymple Road Pavement Rehabilitation and Reconstruction
Role: Superintendents Representative
Duration: January 2008 – March 2008
Summary:
Summary Performance of the contracts required to undertake the construction of the pavement rehabilitation and full reconstruction of the pavement.

Liaison and Supervised with Council and the Contractor on project issues to maintain strong cooperative approach to the delivery of the project that required multiple contractors on a highly trafficked road in a very short timeframe.