Jupiter’s Casino Carpark
Client: | Matrix Group |
Project: | Jupiter’s Casino Carpark Upgrade and Resurfacing |
Role: | Contracts Manager |
Duration: | May 2009 – July 2009 |
Summary: |
Re-surfacing and upgrade project for the Jupiter’s Casino Carpark
Contracted to undertake a review of the pavement failures at the site for the information of Matrix and others. Installation of new street lighting and access gates prior to the re-surfacing of the existing carparking area. In the initial stages of the project PDM recommended the geotechnical investigation and design review of the existing carpark pavement. The objective of the investigation and review was to highlight the soundness of the constructed pavement for the purposes of upgrading the pavement with the proposed works. This request was not acted upon by direction of the client. |